2.
Power Supply/CNC Control.
- Disassemble
sheet metal and remove printed circuit
boards. Steam clean PCBs and electronic
box to remove oil, dirt and grinding
dust. Dry for two days then reassemble.
- Inspect
all connections, cables, fiber optics,
relays, transformers and switches.
- Conduct
diagnostics tests on CNC control and
power supply.
- Upgrade
to 3-1/2" floppy disk drives as
required.
- Install
H-Tec software as required.
|